Rebuilding Memorial Wharf to Battle Rising Seas
The project to renovate and raise Memorial Wharf in Edgartown had hoped to be completed by Memorial Day weekend.
Mark Alan Lovewell
The project to renovate and raise Memorial Wharf in Edgartown had hoped to be completed by Memorial Day weekend.
Mark Alan Lovewell
Barges have been familiar presence in Edgartown harbor this winter.
Mark Alan Lovewell
Reconfigurations on the Chappy ferry side of the wharf.
Mark Alan Lovewell
Project marks the third major climate change-inspired project undertaken on the Edgartown harbor.
Mark Alan Lovewell
Project marks the third major climate change-inspired project undertaken on the Edgartown harbor.
Mark Alan Lovewell
Unforeseen issues included a piling that was too close to an underwater conduit.
Mark Alan Lovewell
Mark Alan Lovewell
The delay will not change the operation of the Falmouth-Edgartown ferry.
Mark Alan Lovewell
New dock for harbor's fishing fleet.
Mark Alan Lovewell
Finishing up some of the upper deck’s supports.
Mark Alan Lovewell
Steve Ewing is chairman of the Memorial Wharf committee.
Mark Alan Lovewell
Upper deck is popular destination to watch harbor activities.
Mark Alan Lovewell
Wharf project is major public works effort by the town in the face of rising seas.
Mark Alan Lovewell
Wharf project is major public works effort by the town in the face of rising seas.
Mark Alan Lovewell
The Memorial Wharf project which began last fall and includes raising the wharf by about a foot and a half continues. It is expected to be completed mid June now.